Official DLD Construction Status — June 2026
Data sourced directly from the **Dubai Land Department** (dubailand.gov.ae) — the government authority for all UAE real estate projects.
---
Grand Polo: All 13 Sub-Projects
| Sub-Project | DLD Number | Completion | Status |
|------------|-----------|-----------|--------|
| **Selvara 2** | #3823 | **4.04%** | Active |
| Selvara 3 | #3866 | 2.98% | Active |
| **Montura** | #3700 | 2.88% | Active |
| Selvara 4 | #3875 | 2.88% | Active |
| Selvara | #3822 | 2.81% | Active |
| Chevalia Estate | #3699 | 2.28% | Active |
| Montura 2 | #3704 | 1.99% | Active |
| Chevalia Fields | #3701 | 1.36% | Active |
| Montura 3 | #3703 | 1.06% | Active |
| Equiterra 2 | #4162 | 1.04% | Active |
| Equestra | #4186 | 1.02% | Active |
| Equiterra | #4185 | 0.83% | Active |
| Chevalia Estate 2 | #4067 | 0.55% | Active |
---
What This Means
**Early Construction Phase**
All 13 Grand Polo sub-projects are registered and active with the DLD — a significant milestone. Construction is in the earliest stages, with earthworks and foundation work underway across the estate.
**Selvara 2 Leads the Pack (4.04%)**
The most advanced phase. Selvara's location within the Grand Polo masterplan positions it as one of the first residential clusters. Early buyers here will see the fastest construction progress.
**Chevalia Estate — The Signature Address**
At 2.28% completion with two additional phases registered (Chevalia Fields and Chevalia Estate 2), Chevalia represents the estate's largest residential cluster. These are premium equestrian-facing villas with direct paddock access.
---
Arabian Ranches Context
Grand Polo sits within **Arabian Ranches**, one of Dubai's most established communities. Recent DLD data shows:
| Arabian Ranches Phase | Completion |
|----------------------|-----------|
| Anya | 95.06% |
| Anya 2 | 94.93% |
| Multiple phases | 100% (Completed) |
Arabian Ranches has a proven track record of developer delivery. Grand Polo benefits from this established infrastructure — schools, retail, golf, and equestrian facilities already operational.
---
DLD Escrow Protection
All Grand Polo payments are held in DLD-regulated escrow accounts:
1. **Developer paid on milestones** — Funds released only when construction targets are verified
2. **Full buyer protection** — DLD guarantees refunds for cancelled projects
3. **Government-audited** — Completion percentages verified by independent surveyors
---
Estimated Timeline
Based on current construction pace and Arabian Ranches historical delivery patterns:
| Milestone | Estimated |
|----------|----------|
| Foundation completion | Q3—Q4 2026 |
| Structural framework | Q1—Q2 2027 |
| First handovers | Q4 2027 — Q1 2028 |
*Timelines are estimates. Actual progress may vary based on construction conditions.*
---
Register Your Interest
Be among the first to access Grand Polo inventory as construction advances:
📞 **+971 52 691 9169**
🌐 **thegrandpolo.com**
*Last updated: June 17, 2026. Data source: Dubai Land Department.*